Arizona requires buried utility lines to be marked before anyone digs, from a homeowner setting fence posts to a crew digging a drywell. It's free.

The rules

Arizona 811 at a glance
QuestionAnswer
Who has to call?Homeowners and contractors alike (Arizona Corporation Commission)
Cost?Free; utilities mark their own lines
How long to mark?No later than two working days (A.R.S. 40-360.22)
When can digging start?After marking is complete, or once told none is needed
How long are marks good?15 working days
Big projects?Notice at least 15 business days or 21 calendar days ahead
Penalty?Up to $5,000 per violation

Arizona 811 was called Arizona Blue Stake until 2014.

Yellow mini excavator in a garden
Even small digs need marks first. Stock photo: Alexas_Fotos / Pixabay, Pixabay Content License.

On a Goodyear site

  • Get the ticket in before the machine is booked.
  • Keep the marks visible for the length of the job, and refresh them if work runs past 15 working days.
  • Tell the contractor about anything you had buried privately.

Questions and answers

How long does Arizona 811 have to mark lines?

No later than two working days, under A.R.S. 40-360.22.

Get it quoted

Send the details or call, and a local excavation contractor will follow up with you. Quote requests are free.

Call (623) 294-2358

Voicemail? Leave your name, phone number, the site address and a short description of the work.