In Goodyear, most new development keeps its stormwater on site. The city's Engineering Design Standards and Policies Manual (Chapter 3, 2017) sets how much, how deep, and how fast it has to drain.

Retention basin cross-section (simplified, not to scale)Side slopes6:1 near public areas, up to 4:1 elsewhere3 ftavg maxHolds the 100-year, 6-hour storm; drains within 36 hours
Simplified, not to scale. Goodyear's figures: 100-year, 6-hour storm, 3-foot average depth, 36 hours to drain.

The numbers

Retention standards (Goodyear stormwater manual, Chapter 3)
ItemGoodyear standard
Storm to retain100% of the 100-year, 6-hour storm
Average high-water depthNo more than 3 feet
Within 10 feet of right-of-wayNo more than 1.5 feet, unless the basin is fenced
Without a positive disposal methodNo more than 1 foot deep and 1,000 cubic yards
Side slopes by public areas6:1 or flatter
Side slopes by walls or fences with limited accessUp to 4:1
Time to drainWithin 36 hours

Retained stormwater can't be discharged onto a city street, gutter or alley.

Custom lots are different

Goodyear's custom-lot grading checklist says no on-lot retention is allowed on lots under one acre. Those lots drain to the street at a minimum 1% slope instead. See custom lot grading.

Bulldozer pushing earth on a construction site
Basins are cut and shaped with dozers and excavators, then checked against the plan. Stock photo: Bru-nO / Pixabay, Pixabay Content License.

Who signs off

Drainage reports are signed and sealed by a registered professional engineer, and as-built drawings by a qualified professional registered in Arizona. The excavation contractor builds to those plans.

Cost

Angi's Phoenix guide lists grading and leveling at $415 to $6,720, leveling at $5 to $15 per cubic yard and machine time at $105 to $260 an hour. Engineering, drywells and landscaping are extra.

Questions and answers

What storm does a Goodyear retention basin have to hold?

Goodyear's stormwater manual calls for on-site retention sufficient to hold 100% of the 100-year, 6-hour storm.

How fast must a retention basin drain in Goodyear?

The manual says retained or detained stormwater must be disposed of within 36 hours.

Get your basin quoted

Send the details or call, and a local excavation contractor will follow up with you. Quote requests are free.

Call (623) 294-2358

Voicemail? Leave your name, phone number, the site address and a short description of the work.

Get an excavation quote

Your details go to a local contractor so they can reach you. Privacy